I-40 Repaving Project Could Be Finished Ahead of Schedule

Posted September 13, 2007

Map Marker  Find News Near Me

— The $21 million project to repair a botched paving job on a nearly 11-mile stretch of Interstate 40 through Durham County could be complete by the end of November – six months ahead of schedule.

"The I-40 overlay project has gone very well," Dennis Jernigan, an engineer with the state Department of Transportation, said Thursday. "The contractor is currently slightly ahead of schedule."

Lane Construction Corp., of Meriden, Conn., began repaving the roadway in April and was scheduled to work through November, then resume in March 2008.

Dry weather has helped put crews ahead of schedule, Jernigan said. When the project began in April, weather too cold for paving and rain had dogged the work schedule, but this summer's drought ended that interference.

"We are approximately 70 percent complete," Jernigan said. "The majority of weekend lane closures have been exhausted, so hopefully, the impact will be just a little while longer."

Nighttime and weekend-long lane closures on the stretch of pavement have caused hassles for thousands of drivers in recent years.

In 2003, crews began widening I-40 to six lanes from the Durham Freeway to U.S. Highway 15-501. The project, which cost $50 million, was completed about a year later, but in Summer 2005, the top layer of the two old lanes of the interstate began crumbling.

The DOT discovered that expansion joints in the 10.6-mile stretch had been improperly constructed when new concrete was laid on top of the old. The third lane in each direction was completely new and did not have to be dug up this year.


Please with your account to comment on this story. You also will need a Facebook account to comment.

Oldest First
View all
  • SaveEnergyMan Sep 15, 2007

    Well, at least there is a good side to this drought. As to the thought of installing desalination plants and getting ocean water -- are you nuts??!! It's 150 miles to the ocean and that would cost billions, plus the cost of pumping. Not a viable option. Smart growth is much better.

  • texlady Sep 14, 2007

    The applause should be for Lane Construction/Rea Contractor they are the ones who did the job.

  • texlady Sep 14, 2007

    Wow, It seems no matter what, you people are never happy. You have to have some thing to complain about.

  • TheWB Sep 14, 2007

    I-40 Repaving Project Could Be Finished Ahead of Schedule

    Jeeze, you'd think they would take their time, this time.

  • jahausa Sep 13, 2007

    $21 million to fix a messed up $50 million project. Hapless morons.

  • daddyham Sep 13, 2007

    It sounds like DOT is looking for applause. Not from me, thank you.

  • mrtwinturbo Sep 13, 2007

    What is costs to take care of this highway every three years you could have built two desalination plants and have the needed water that the triangle needs so bad

  • 37 Sep 13, 2007

    Well, "early" is certainly a relative term with this project, isn't it? Considering the whole project is a result of poor workmanship the first time, this whole endeavor should not have been necessary.