Log in to WRAL.com with one click using your favorite social network:
OR
Log in using your WRAL.com account:



Wrong email/password combination.

Forgot password?

Register with WRAL.com using your favorite social network:
OR
Register for a WRAL.com account using our web form.

Login Options

1:39 p.m. • 2-12-12

Weather Forecast for Raleigh

  • Today: Clear.
    • Hi: 41° F
  • Mon: Partly Cloudy.
    • Hi: 50° F
  • Tue: Rain.
    • Hi: 53° F

Other Locations

> 7 Day Forecast

Doppler Image

Marketplace Links

Social Links

Main Menu

Part of I-40 East closed overnight


e-mail print friendly
Part of I-40 East closed overnight
Part of I-40 East closed overnight

The eastbound lanes of Interstate 40 at N.C. Highway 54 (Chapel Hill Road) will be closed until 5 a.m. Friday.

The closure started at 9 p.m. Thursday.

Motorists traveling south on N.C. 54 should use the northbound on-ramp to I-40 East until midnight Thursday.

After midnight, motorists should take Exit 290 from I-40 to N.C. 54, cross over N.C. 54 and proceed back down the on ramp onto I-40 East.

Police officers will be present at the interchanges to direct traffic.

The North Carolina Department of Transportation is is closing the lanes to begin installation on two conveyor belt systems at the N.C. 54 interchange that will transport stone and asphalt to the median area of I-40.

Contractors say the conveyor belt will help crews haul material into the median for construction work later without stopping traffic. It is estimated the belt will eliminate 237 lane closures and nearly 12,000 truckload trips.

The company working on I-40, S.T. Wooten Corporation, also worked on the Highway 98 bypass in 2005. S.T. Wooten installed a similar conveyor belt over Capital Boulevard, which reduced the number of times crews had to close any lanes.

“It minimizes greatly the amount of lane closures nightly,” said Michael Alford, of S.T. Wooten.

"If it does improve it and it's short term and gets done quickly, I think that's better," said driver James Edick.

Once installed, crews could start using the conveyor belts in the spring and keep the I-40 widening project on schedule.


View I-40 lanes closed in a larger map

e-mail print friendly

1 Comment


WRAL.com welcomes your comments on this story. All comments are moderated prior to publication based on our posting guidelines. Please review them prior to posting and if your message is not approved.

View Comments 1 COMMENTS

This story is closed for comments. Comments on WRAL.com news stories are accepted and moderated between the hours of 8 a.m. and 8 p.m. Monday through Friday.

Latest Comments
It looks pretty neat and seems like the smart thing to do.

View Comments 1 COMMENTS
Report It

Multimedia

Click Here