WAKE COUNTY — I am truly thankful for the rain.
About 45,000 of the 50,500 lights are plugged in. Began testing computer control at load, and the rains came. I will finish up over the next couple of days as the weather allows.
Specifically, Controllers 1-5, and 8 are fully wired to lights. 7 is mostly complete, and 6 is partially complete.
I'll update via the comments in this blog post, and will create a new blog post when I'm ready to go.
Alas, I must return to work tomorrow, so slicing off the few hours I need to wrap it up will be a challenge.
Stay tuned!